What is often referred to as fixture installation?

Prepare for the NCCER Plumbing Level 2 Test with flashcards and multiple choice questions. Each question includes hints and explanations for better understanding. Get exam-ready and boost your confidence!

Fixture installation is commonly known as finish work. This phase in plumbing involves the installation of fixtures such as sinks, toilets, faucets, and other visible components that complete the plumbing system in a building.

Finish work is critical because it ensures that all the plumbing fixtures are properly and securely attached, and it includes tasks like connecting the fixtures to the water supply and drainage systems. This stage typically occurs after the rough-in work, where the basic plumbing lines are installed but before the final inspection, which verifies the entire system's compliance with code and functionality.

While final inspection refers to the assessment phase after all work is completed and operational, rough-in work includes the underground piping and initial system setup, and service work involves ongoing maintenance and repairs after the installation is complete. Thus, identifying fixture installation as finish work highlights the importance of this stage in providing a complete and functional plumbing system.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy