If the backflow prevention specified on the construction drawings differs from what is recommended in your local applicable code, you should submit an?

Prepare for the NCCER Plumbing Level 2 Test with flashcards and multiple choice questions. Each question includes hints and explanations for better understanding. Get exam-ready and boost your confidence!

Submitting a Request for Information (RFI) is the appropriate course of action when there is a discrepancy between the backflow prevention specified on construction drawings and the requirements outlined in local applicable codes. This process allows you to formally seek clarification or additional information regarding the specified materials, ensuring compliance with safety regulations and standards.

The RFI is a crucial part of construction communication as it helps to address uncertainties that may arise during a project. By submitting an RFI, you can initiate a dialogue with the design team or the authority having jurisdiction, allowing for proper assessments and adjustments before proceeding with construction. This is vital for avoiding delays or compliance issues that can arise from using materials or methods that are not in line with local codes.

Furthermore, the other options do not serve the purpose of addressing the code discrepancy. An Order for Inspection typically pertains to scheduling inspections rather than clarifying design details. A Change Order is used when there is a need to modify the scope, design, or costs of the project, which may not be applicable if you only seek clarification on codes. A Site Update may refer to notifying teams about ongoing work but does not directly address the need for clarification regarding code compliance.